Overview
The
Project Board uses the Project Plan throughout the project to measure overall
progress. As stages are completed or planned in detail the Project Plan must be
updated to reflect the latest understanding of the project, and to allow the
Project Board to revise its expectations.
Context
The
Project Plan is updated based on three documents; the Stage Plan for the stage
that is finishing, the Next Stage
Plan, and any Exception Plan triggered by
Escalating Project Issues. Actuals are taken from the first and the forecast
duration and costs from the last two.
Process Description
The
Project Quality Plan and Project Approach
are re-assessed and refined to
reflect the current understanding of the project, and to form a basis for
updating the Project Plan.
The
Project Plan is updated based on the actual costs and schedule from a completed
Stage or Exception Plan, the new detail of activities and costs from the
Next Stage Plan (unless there is no next Stage or Exception
Plan) and any acquired
knowledge about the project. The last might be information about changes which
have been agreed by the Project Board and which will cause activities in the
Next Stage Plan. The Project Manager should describe in the End Stage Report
(or Exception Report) why any change to the
Project Plan has occurred.
Responsibilities
The
Project Manager is responsible, assisted by project
support, and the work
checked out by those with project assurance responsibility.
Management information |
Usage |
Explanation |
Current Stage Plan |
Input |
The results of the current stage may affect the project planning |
Input |
The extra detail in the Stage Plan may reveal the need to modify the Project Plan |
|
Update |
Events may have occurred which modify the approach |
|
Update |
Quality results so far may show the need to adjust the Plan |
|
Update |
Revised in the light of the actuals from the current stage and the forecast of the Next Stage Plan. Also updated to reflect any changed or extra products sanctioned by the Project Board |
|
How reliable are the
figures for cost and schedule for the stage just completing? (Especially if
fed information from Team Plans.) |
|
How do the results of the
stage impact the Project Plan? |
|
How does the Next Stage Plan
impact the Project Plan, Business Case and risks? |
|
Did any other information
come out of the last stage that will impact later stages of the project? |