Form Type |
|
A
mandatory plan which provides a statement of how and when
a project's objectives are to be achieved, by showing the
major products, activities and resources required on the
project. It provides
the Business Case with planned project costs, and
identifies the management stages and other major control
points. It is used by the Project Board as a baseline
against which to monitor project progress and cost stage
by stage. It forms part of the Project Foundation
Document and will contain the following. |
|
Project Name |
|
|
|
Date Raised |
|
Raised by |
|
Giving
a brief description of what the plan covers |
|
|
|
Project
pre-requisites |
containing
any fundamental aspects which must be in place at the
start of the project, and which must remain in place for
the project to succeed |
|
|
External
dependencies |
|
|
|
Planning
assumptions |
|
|
|
Project Plan |
covering: |
Project
level Gantt or bar chart with identified management
stages |
|
Project
level Deliverables Descriptions |
|
Project
level activity network |
|
Project
financial budget |
|
Project
level table of resource requirements |
|
Requested/assigned
specific resources |
|