Form Type |
|
An
Exception Report is produced when costs and/or timescales
for an approved Stage Plan are forecast to exceed the
tolerance levels set. It is sent by the Project Manager
in order to apprise the Project Board of the adverse
situation. An
Exception Report will normally result in the Project
Board asking the Project Manager to produce an Exception
Plan. |
|
Project Name |
|
|
|
Form Number |
|
Date Raised |
|
Raised by |
|
A description of the cause of the
deviation from the Stage Plan |
|
Consequences
of the deviation
|
|
The available
options
|
|
The effect of
each option on the Business Case, risks, project and
stage tolerances
|
|
The
Project
Manager's recommendations.
|
|