A
stage is deemed to be in exception as soon as current forecasts for the end of
the stage deviate beyond the delegated tolerance bounds. The project is in
exception if the whole project is likely to go beyond tolerance bounds.
If
either stage or project is forecast to deviate beyond its agreed tolerance
boundaries, it no longer has the approval of the Project
Board. A new plan must
be presented to take the place of the current plan.
The
deviation should have been recognised during Controlling a Stage. The Project
Manager will have brought the situation to the attention of the Project Board
through an Exception Report. The
Project Board will have requested the
Project
Manager to produce an Exception Plan. The Exception Plan will then be presented
to the Project Board at a Mid-Stage Assessment.
If
a stage or the project is forecast to go outside the tolerances agreed with the
Project Board when the plan was approved, and the situation cannot be
rectified, the Project Manager has no further mandate to carry on with the
work. The Project Board must be advised of the situation at the earliest
possible moment.
The
Exception Plan will have the same structure as other PROMISE
plans. It
should run from the present time to the end of the stage. If it is the Project
Plan that is in exception, a revised Project Plan should be created, taking
into account the actuals to date.
The
Project Manager is responsible for producing Exception Plans with the help of
any project
support, and would work with those responsible for project
assurance to check it.
Management information |
Usage |
Explanation |
Current Stage Plan |
Input |
This is the plan from which the deviation has occurred and which will define the tolerances and the extent of the deviation. It can also be used to extrapolate what would happen if the deviation were allowed to continue |
Input |
This may contain details of the reasons for the project or stage going into exception |
|
Input |
Contains details of all actions raised, whether open or closed. |
|
Input |
This warning should have been sent to the Project Board at the first indication of a probable deviation. It is the trigger for the start of this process |
|
Update |
What is the impact of the deviation and Exception Plan on the risks? |
|
Exception Plan |
Output |
The product of this process, a plan which replaces the current Stage Plan |
|
Has the deviation
adversely affected the Business Case for the project? |
|
What extra risks does the
approved option bring? |