A
Project Manager's job can easily become dominated by day-to-day problem
solving. This can mean that overall progress is not checked regularly. If the
project is not checked on a timely basis, there is a danger that it will get
out of control. There needs to be a balance between planning ahead and reacting
to events.
There
will often be a need to incorporate unplanned activities.
A
regular check must be kept on external events that could affect the project.
This
process provides the means for a regular assessment of the stage status. The
process decides if:
|
Further work is necessary |
|
Any plan modifications
are required. |
If
the stage and project are within tolerance, the next actions are Reporting
Highlights to the Project Board for the next tranche of work.
If
corrective actions are needed, and the stage and project are predicted
to stay within tolerance, the next process will be Taking Corrective Action.
The
Project Manager may seek guidance from the Project Board about any
Project
Issue (Escalating Project Issues) and should always do so if the
stage or project is predicted to go outside tolerance. Another reason for
reference to the Project Board would be that a
Project Issue affects policy
external to the project.
Where
Configuration Management is in operation a status account would be provided for
the Project
Manager, showing the planned products and their status. If it were
the last stage of the project, the Project Manager would ask for a status
account for all products to confirm that they are all approved.
The
first objective of this process is to check periodically that the current stage
is kept within the tolerances set down by the Project Board by:
|
Reviewing progress
against the Stage Plan |
|
Reviewing resource
utilisation and future availability |
|
Reviewing the effect of
Project Issues on change budget and Stage and
Project Plans |
|
Establishing whether the
stage will go outside the tolerances or not |
|
Passing Project
Issues
likely to cause tolerance to be exceeded to the Project Board - via
Escalating Project Issues - for consideration. |
If
corrective action is needed, but the Stage is forecast to stay within tolerance,
the action can be taken by the Project
Manager, as described in Taking
Corrective Action.
The
second objective of the process is to review the project status, specifically:
|
Checking that the
Business Case is still valid |
|
Reviewing the Risk Log for
possible changes |
|
Establishing whether or
not the project will go outside the tolerances. |
In
order to achieve these objectives, various steps have to be undertaken:
|
Identify any variation
between plan and actual progress |
|
Check for any variation
in the expected future resource availability |
|
Assess any current risk
to the Stage Plan for any change to the exposure |
|
Check the updated Stage
Plan for any new risks |
|
Review external
developments for any impact on the project |
|
Check to see if anything
has happened within the project or externally which will impact the Business
Case |
|
Assess whether the stage
will stay within tolerances |
The
Project Manager is responsible, supported by any support roles and those with
assurance responsibilities. It may be necessary on occasions to consult Project
Board members for guidance, especially with regard to Project
Issues or
resource shortfalls or external events that may impact the Business Case or
Risk Log.
Management information |
Usage |
Explanation |
Input |
This will show the current situation regarding all Project Issues. These may be needed for reference when deciding on appropriate action to deal with them |
|
Input |
This will show the current situation regarding all Project Actions. |
|
Input |
This product shows the current understanding of the problems and threats to the project |
|
Input |
Data to check if any stage problem (or potential change) would have an impact on the Project Plan |
|
Update |
The latest information regarding progress on the work currently in hand, or completed since the process was last conducted or since the Stage Plan was last reviewed. The Stage Plan provides the baseline against which progress is measured, and against which the meeting of the stage tolerances is measured. The product will be updated with any minor amendments |
|
Plan deviation |
Output |
The information to be passed to Taking Corrective Action |
Stage Status information |
Output |
This information goes forward to Reporting Highlights |
Stage End Notification |
Output |
Trigger for Reporting Stage End |
Notification of Project end |
Output |
Trigger for Closing a Project |
Proposed plan revision |
Output |
Trigger, plus information for Escalating Project Issues |
|
Have all the aspects of
progress, Project Issues, Actions and risk been considered? Have they been
balanced to create a complete picture of the current status of the project? |
|
Have all reasonable
courses of action been considered when deciding on the best way forward? |
|
Has the project been
honest with itself concerning the likelihood of staying within tolerance? |
|
Do the estimates to
complete seem reasonable in the light of all the information available? |