Introduction to Processes

Objectives

This chapter of the manual discusses the processes involved in managing a PROMISE Project, and how those processes link with each other. The processes indicate the normal content of a PROMISE project. Any project run under PROMISE will address each of these processes in some form. HOWEVER, the key to successful use of this process model is it’s tailoring. Each process must be approached with the question 'How extensively should this process be applied on this project?'

The PROMISE Process Model

There are eight major processes, each made up of a collection of processes. The major processes are:

*

Starting a Project

*

Project Kick Off

*

Directing a Project

*

Controlling a Stage

*

Product Release

*

Stage Transitioning

*

Closing a Project

*

Planning.

Planning is used throughout the process model.

These processes link to a range of project management techniques, some of which are specific PROMISE techniques and are defined within the manual, and some of which are generic and generally used techniques that are not defined within the manual.

Structure of Each Process Description

Below are outline descriptions of each of the processes in the process model. Each process description has the following structure and format.

Overview

Under this heading the following questions are addressed:

*

Why have this process?

*

What is it aiming to achieve in project management terms?

*

Why is this process fundamental to good project management, and hence a minimum requirement of PROMISE?

Context

This section puts each process in context with the other processes, and with activities going on outside the scope of project management as defined by PROMISE.

Process description

This section describes the process by explaining the objectives and how the process fulfils the fundamental principles, and gives a description of the steps involved in carrying out the process.

No attempt has been made to lay out the steps in a strict sequence, since such a hard and fast sequence seldom exists. However, they have been listed in as logical a sequence as possible.

Responsibilities

This section specifies who should be accountable for the successful conduct of the major process, and responsible for its management. These are only stated for the processes, as it is at that level that responsibilities can be decided.

Information needs

This section contains a table of the important information required for the process to function and achieve its objectives. Some entries will be products such as plans and reports; others are in the nature of decisions.

Key criteria

This section highlights the main issues that will dictate the ultimate success or failure of the process.

Summary of the Processes

Directing a Project

 Directing a Project runs from the start-up of the project until its closure.

This process is aimed at the Project Board. The Project Board manages by exception, monitors via reports and Project Controls through a number of decision points.

The key processes for the Project Board break into four main areas:

*

Initiation (starting the project off on the right foot)

*

Stage boundaries (commitment of more resources after checking results so far)

*

Giving direction (monitoring progress, providing advice and guidance, reacting to exception situations)

*

Project closure (confirming the project outcome and bringing the project to a controlled close).

This process does not cover the day-to-day activities of the Project Manager.

Pre Project Preparation

This is the first process in PROMISE. It is a pre-project process, designed to ensure that the pre-requisites for initiating the project are in place. The process expects the existence of a rudimentary Project Directive that defines in high-level terms the reason for the project and what outcome is sought. Pre Project Preparation should be very short. The work of the process is built around the production of three elements:

*

Ensuring that the information required for the Project Directive is available

*

Defining and appointing the Project Management Team

*

Creating the Initiation Stage Plan.

Project Kick Off

The objectives of Project Kick Off are to:

*

Agree whether or not there is sufficient justification to proceed with the project

*

Establish a stable management basis on which to proceed

*

Document and confirm that an acceptable Business Case exists for the project

*

Ensure a firm and accepted foundation to the project prior to commencement of the work

*

Agree to the commitment of resources for the first stage of the project

*

Enable and encourage the Project Board to take ownership of the project

*

Provide the baseline for the decision-making processes required during the project's life

*

Ensure that the investment of time and effort required by the project is made wisely, taking account of the risks to the project.

Stage Transitioning

 This process provides the Project Board with key decision points on whether to continue with the project or not.

The objectives of the process are to:

*

Assure the Project Board that all deliverables planned in the current Stage Plan have been completed as defined

*

Provide the information needed for the Project Board to assess the continuing viability of the project

*

Provide the Project Board with information needed to approve the current stage's completion and authorise the start of the next stage, together with its delegated tolerance level

*

Record any measurements or lessons that can help later stages of this project and/or other projects.

Controlling a Stage

This process describes the monitoring and control activities of the Project Manager involved in ensuring that a stage stays on course and reacts to unexpected events. The process forms the core of the Project Manager's effort on the project, being the process that handles day-to-day management of the project.

Throughout a stage there will be a cycle consisting of:

*

Authorising work to be done

*

Gathering progress information about that work

*

Watching for changes

*

Reviewing the situation · reporting

*

Taking any necessary corrective action.

This process covers these activities, together with the on-going work of risk management and change control.

Product Release

The objective of this process is to ensure that planned products are created and delivered by:

*

Ensuring that completed products meet quality criteria

*

Obtaining approval for the completed products.

*

Transitioning the product into operation

Closing a Project

The purpose of this process is to execute a controlled close to the project.

The process covers the Project Manager's work to wrap up the project either at its end or at premature close. Most of the work is to prepare input to the Project Board to obtain its confirmation that the project may close.

The objectives of Closing a Project are, therefore, to:

*

Check the extent to which the objectives or aims set out in the Project Foundation Document have been met

*

Confirm the extent of the fulfilment of the Project Foundation Document and the Customer's satisfaction with the deliverables

*

Obtain formal acceptance of the deliverables

*

Ensure to what extent all expected products have been handed over and accepted by the Customer

*

Confirm that maintenance and operation arrangements are in place (where appropriate)

*

Make any recommendations for follow-on actions

*

Capture lessons resulting from the project and complete the Lessons Learned Report

*

Prepare an End Project Report

*

Notify the host organisation of the intention to disband the project organisation and resources.

Planning

Planning is a repeatable process, and plays an important role in other processes, the main ones being:

*

Planning an Initiation Stage

*

Planning a Project

*

Planning a Stage

*

Producing an Exception Plan.

PROMISE provides a product-based start to the planning activity. It also provides a planning framework that can be applied to any type of project. This involves:

*

Establishing what products are needed

*

Determining the sequence in which each product should be produced

*

Defining the form and content of each product

*

Resolving what activities are necessary for their creation and delivery.