Overview
Even
when a stage is proceeding according to plan and within tolerance, there may be
a need for the Project Board to be consulted. Such occasions might be:
|
For advice on direction
when options need clarifying |
|
When the impact of events
external to the project needs to be considered |
|
To resolve resourcing
issues which would affect tolerance |
|
To resolve areas of
conflict |
|
Organisational changes
within the project. |
It
is also possible that, during a stage, the Project
Board. itself will need to
pass information to the Project Manager about external events and its own
changing requirements.
This
is a process that may be needed at any point during the project. It could be
prompted by an external event, or by information or circumstances arising from
within the project.
The
objectives are for the Project Board to:
|
Ensure that the project remains
focused on the business objectives set, and remains justified in business
terms |
|
Ensure that the stage is
progressing according to plan |
|
Ensure that changes in
the corporate or programme environment which may impact on the project are notified
to the Project Manager and appropriate action is taken |
|
Ensure that the project
is kept informed of external events which may affect it |
|
Make decisions on Project
Issues or Exception Reports which are beyond the
Project
Manager's authority |
|
Advise the Project
Manager of any change to Project Board personnel |
|
Keep corporate or
programme management informed about project progress. |
The
above objectives should be achieved without the need for the Project Board to
interfere in the project beyond the Project Controls and reports it has agreed
with the Project
Manager.
The
Project Board should receive regular Highlight
Reports from the Project Manager
with a frequency agreed for the current stage.
The
Project Board should ensure that any serious risk situations are being
monitored sufficiently regularly to keep the risks under control. The Project
Manager will refer situations to the Project Board via an Exception Report
where a stage is forecast to exceed its tolerance.
Within
its delegated limits of authority there may be occasions when the Project Board
may choose to:
|
Ask the Project Manager to
submit an Exception Plan for the remainder of the stage to reflect the new
situation (see Producing an Exception Plan
) |
|
Reduce the scope of
project expectations to bring it back within tolerance using change control
(see Producing an Exception
Plan) |
|
Abandon the project (see
Closing a Project). |
Project
Issues may arise on which the Project Manager needs guidance. The
Project Board
provides this guidance based on the impact of the Project Issue in question on the
Business Case and risks. Project Issues include all Requests For Change and
Non-Compliancies raised. As these represent changes to the agreed Project
Foundation Document, it is a Project Board function to approve or reject any
changes. Agreed changes may need extra time and/or funds.
Where
a Project Issue goes beyond the brief held by the Project
Board, the Project
Board has the responsibility of seeking a decision from corporate or programme
management.
The
Project Board has the responsibility to obtain any extra or changed resources
that occur as a result of agreements with the Project Manager on issues raised.
The Project Board must ensure that external events that could impact the
project are monitored adequately and dealt with effectively.
There
will be times when a Project Board has to be changed. This may be because a
current member changes job, or extra Customers or
Suppliers may be found and
they need representation on the Project
Board. It is the Project
Board's job to
notify the Project
Manager. The Project Manager must then agree a job
definition with the new member(s).
This
is a Project Board responsibility. It may look to share some of this
responsibility with those with project assurance responsibilities.
Management information |
Usage |
Explanation |
Input |
Regular feedback on progress from the Project Manager |
|
Input |
Early warning of a deviation. May trigger the creation of an Exception Plan |
|
Request for advice |
Input |
Situations where a decision is needed which is beyond the authority of the Project Manager |
Information from external sources |
Input |
Either feedback from a Project Board request or new information which affects the direction of the project |
Corporate or Programme Management Reports |
Output |
Feedback on project progress |
Project Board direction |
Output |
Guidance and advice in reaction to the inputs noted above |
Premature Close |
Output |
Closing the project before its expected end |
|
Does the Project Manager
know how to contact Project Board members in the event of problems arising? |
|
Are Project Board members
aware of the need to react quickly to issues raised? |
|
Are Project Board members
committed to prompt reading of Highlight
Reports and to timely response to
them? |