Confirming Project Closure

Overview

There needs to be a formal hand-over of responsibility and ownership of the project's products to the ultimate users.

For most final products there must be a reliable operational and support environment in place.

Every effort should be made to pass on any lessons that have been learned from the project.

Context

The process is triggered. by the Project Manager carrying out the activities and producing the management products of Closing a Project. It is the last work done by the Project Board prior to its disbandment.

Process Description

The project needs to be closed down in an orderly manner.

The objectives of this process are to:

*

Ensure that the project has a clearly defined end and an organised hand-over of responsibility to the group(s) who will use, support and sustain the products

*

Release the resources provided to the project

*

Gain formal acceptance from the Customer that the acceptance criteria set down at the outset have been met adequately

*

Direct any chances which have not been implemented to an appropriate authority for attention

*

Establish a future method for verifying that the. project has produced the. desired benefits

*

Recommend closure of the project to corporate or programme management.

To achieve these objectives, various steps need to be undertaken:

*

Ensure that all the completed products have been approved by the Customer or are covered by approved waivers (if there have been any waivers, these may also be covered in Follow-on Action recommendations)

*

Ensure that, where appropriate, the resulting changes in the business are supported and sustainable

*

Ensure Follow-on Action Recommendations have been distributed correctly.

*

Approve the Lessons Learned Report for distribution.

*

Prepare closure notification.

*

Publish and distribute the plans for any Post Implementation Review.

Responsibilities

This is the responsibility of the Project Board, supported by those with project assurance responsibilities.

If a Post Implementation Review is set up, it is the responsibility of the Project Board to ensure that the person responsible for its conduct is properly briefed and that accountability is passed to that person.

Information Needs

Management information

Usage

Explanation

Project Foundation Document

Input

Used as the baseline against which to assess how far the project deviated from its initial basis. Also contributes some of the information against which to judge the success of the project

Operational and maintenance acceptance

Input

Confirmation that the final product can be used and supported

Project Closure recommendation

Input

Assurance from the Project Manager that everything has been done

End Project Report

Input

More information on which to judge the success of the project

Customer acceptance

Input

Confirmation that the Customer accepts the products

Follow-on Action recommendations

Approval

Recommendations for all pended issues and other future actions

Post Implementation Review Plan

Approval

Suggested plan for assessing the achievement of project benefits. Ratified by the Project Board to be passed on to the people responsible for carrying it out

Lessons Learned Report

Approval

Project lessons that have been learned which might be useful to pass on to other projects

Project Closure Notification

Output

Notification that facilities and support can be withdrawn

Key Criteria

*

Have the results and products been accepted, and are they no longer dependent on work that is part of this project?

*

Is the business ready to support, sustain and further develop the environment and products delivered? Are the customers content with the results and products?