Overview
There
needs to be a formal hand-over of responsibility and ownership of the project's
products to the ultimate users.
For
most final products there must be a reliable operational and support
environment in place.
Every
effort should be made to pass on any lessons that have been learned from the
project.
The
process is triggered. by the Project Manager carrying out the activities and
producing the management products of Closing a Project. It is the last work
done by the Project Board prior to its disbandment.
The
project needs to be closed down in an orderly manner.
The
objectives of this process are to:
|
Ensure that the project
has a clearly defined end and an organised hand-over of responsibility to the
group(s) who will use, support and sustain the products |
|
Release the resources
provided to the project |
|
Gain formal acceptance
from the Customer that the acceptance criteria set down at the outset have
been met adequately |
|
Direct any chances which have
not been implemented to an appropriate authority for attention |
|
Establish a future method
for verifying that the. project has produced the. desired benefits |
|
Recommend closure of the
project to corporate or programme management. |
To
achieve these objectives, various steps need to be undertaken:
|
Ensure that all the
completed products have been approved by the Customer or are covered by
approved waivers (if there have been any
waivers, these may also be covered in
Follow-on Action recommendations) |
|
Ensure that, where
appropriate, the resulting changes in the business are supported and
sustainable |
|
Ensure Follow-on Action
Recommendations have been distributed correctly. |
|
Approve the Lessons Learned
Report for distribution. |
|
Prepare closure
notification. |
|
Publish and distribute
the plans for any Post Implementation
Review. |
This
is the responsibility of the Project
Board, supported by those with project assurance
responsibilities.
If
a Post Implementation Review is set up, it is the responsibility of the Project
Board to ensure that the person responsible for its conduct is properly briefed
and that accountability is passed to that person.
Management information |
Usage |
Explanation |
Input |
Used as the baseline against which to assess how far the project deviated from its initial basis. Also contributes some of the information against which to judge the success of the project |
|
Operational and maintenance acceptance |
Input |
Confirmation that the final product can be used and supported |
Project Closure recommendation |
Input |
Assurance from the Project Manager that everything has been done |
Input |
More information on which to judge the success of the project |
|
Customer acceptance |
Input |
Confirmation that the Customer accepts the products |
Follow-on Action recommendations |
Approval |
Recommendations for all pended issues and other future actions |
Approval |
Suggested plan for assessing the achievement of project benefits. Ratified by the Project Board to be passed on to the people responsible for carrying it out |
|
Approval |
Project lessons that have been learned which might be useful to pass on to other projects |
|
Output |
Notification that facilities and support can be withdrawn |
|
Have the results and
products been accepted, and are they no longer dependent on work that is part
of this project? |
|
Is the business ready to support,
sustain and further develop the environment and products delivered? Are the customers content with the results and products? |