Updating a Project Business Case

Overview  
Projects do not take place in a static environment. The environment external to the project changes, as do the nature and timing of the project's products. The Business Case needs to reflect these changes, and must be reviewed and amended to keep it relevant to the project.

Context  
The update of the Business Case and the Project Plan is a cyclic process during stage end processes throughout the project. 

Process Description  
The objective is to re-visit and revise, where necessary, the costs, benefits and timings stated in the Business Case. These may have been affected by internal or external events. Various factors will affect this process including:

*

The final implementation date of the project may have changed, for better or worse, which might affect some or all of the benefits

*

The cost of delivering the outcome might have changed, thus affecting the cost side of the cost/benefit analysis

*

Approved changes will have affected products, hence benefits

*

Externally the corporate or programme environment into which the outcome will be delivered may have changed

*

The situation with regard to external resources or Suppliers may have changed beyond the control of the project.

A revised Business Case is created. The Risk, Actions and Issue Logs are examined to see if anything has changed which might affect the Business Case.

It is worth noting that changes may improve the Business Case, just as well as weaken it.

The Project Board is ordinarily only authorised to continue while the project remains viable (i.e. the benefits will be realised within the cost and time parameters set out in the currently agreed Business Case). If costs and/or time are to be exceeded, or it becomes clear that benefits will be substantially lower than those set out in the Business Case, the Project Board needs to have the revised Business Case approved afresh by corporate or programme management.

Responsibilities
The Project Manager is responsible, assisted by project support, and those with project assurance responsibilities should check out the work.

The project's benefits are a prime responsibility of the Customer.

Information Needs

Management information

Usage

Explanation

Project Plan

Input

Have any changes to the Project Plan been made which affect the Business Case?

Issue Log

Input

Are there any new Issues that threaten (or could improve) the Business Case?

Actions Log

Input

Are any actions outstanding? What is their status?

Risk Log

Update

Are there any new risks that threaten the Business Case?

Business Case

Update

Revised to account for any changes to the project that may affect it

Key Criteria

*

Has anything happened external to the project that affects the Business Case?

*

Has the Project Plan changed such that it impacts the Business Case, for example, in terms of overall cost or the date of the scheduled outcome?

*

Has it become impossible to achieve some or all of the identified benefits?