Broadly, there are two types of risk - Business risk and Project risk.
Business Risk
This
covers the threats associated with a project not delivering products that can
achieve the expected benefits. It is the responsibility of the Project Board to
manage business risks. It includes such areas as:
|
The validity and
viability of the Business Case |
|
Whether the project
continues to support the corporate business strategy, including such elements
as:
|
|
The consequences to the
corporate body of failure or limited success |
|
The stability of the
business areas involved |
|
Programme requirements |
|
Impact on the Customer of
the results of the project |
|
The risks of the end
result meeting the stated requirements, but not fulfilling expectations |
Project Risk
This
is the collection of threats to the management of the project and hence to the
achievement of the project's end results within cost and time. These risks may
be managed on a day-to-day basis by the Project
Board, Project Manager or
Team Manager. Risks will be many and varied, but would include the following broad
categories:
|
Procurement issues,
covering those risks caused by being dependent on a third party, including:
|
|
Organisational factors such as:
|
|
Specialist
issues; there will be a wide variety of issues here because each project has
its own particular specialist elements which bring with them their own risk
elements. However, there are some general issues which will apply to many
project types, such as:
|
It
must be stressed that the above lists are given purely to illustrate the areas
of risk that need to be considered as part of project management. Each project
must be considered in its own right.
Once
identified, risks are not kept separate (e.g. business, project, Stage
Plan).
They are all entered in the one Risk Log that is always reviewed in its
entirety.